We’re excited to bring you the latest updates on ODOM’s construction progress. As part of our semi top-down method, which focuses exclusively on basement construction before moving above ground, we continue to advance deeper into the foundation of this landmark development.

Figure 1: Pre-casting preparation

At Basement Level 3, excavation is now complete, marking a key milestone in our progress. Concrete casting is well underway, with three out of the four planned blocks successfully completed. Work on this level’s fourth and final block is in progress, with formwork and rebar installation currently being carried out in preparation for the next concrete pour.

Figure 2: Rebar Installation

We are getting closer to completing the five basement levels that will serve as the strong foundation for ODOM. Our commitment to quality remains as we carefully execute each phase of construction with precision and efficiency.

Figure 3: Concrete Casting

Thank you for your continued support. Stay tuned for more updates as we advance further into this exciting stage of the project. We look forward to sharing more milestones with you soon!

10

理想的なオフィスの広さを見つけましょう

雇用者は何人ですか?

間取りの種類

しばらくお待ちください
小規模オフィスの例

小規模オフィスの例

中規模オフィスの例

中規模オフィスの例

大規模オフィスの例

大規模オフィスの例

大規模オフィスの例

大規模オフィスの例

広さが の小規模オフィスをおすすめします 60〜90㎡

これによって大体となります ㎡/人 名様では 密度になります

広さが の中規模オフィスをおすすめします 91〜148㎡

これによって大体となります ㎡/人 名様では 密度になります

広さが の大規模オフィスをおすすめします 141〜250㎡

これによって大体となります ㎡/人 名様では 密度になります

広さが の大規模オフィスをおすすめします 887〜1,515㎡

これによって大体となります ㎡/人 名様では 密度になります

相談を予約する