Our piling work continues to surge ahead, with 231 out of 270 piles completed, including an additional 12 piles. These sturdy foundations represent a substantial 86% completion rate, ensuring the structural integrity of our future lifestyle hub. As we near the end of this phase, a new chapter in our construction journey is on the horizon.
Beneath the surface, construction of the Diaphragm Wall, our underground support system, is well underway. With 41 out of 48 panels completed, we’re at 85% progress. Each panel contributes to the solid foundation of our structure, woven together like a durable fabric built to last.
With the piling phase wrapping up, our focus shifts towards basement construction, laying a solid groundwork for future stages of the project. Meanwhile, behind the scenes, our dedicated team is hard at work fabricating rebar cages and pouring concrete, ensuring the resilience and longevity of the ODOM project.
Your unwavering support propels us forward as we continue to reach these construction milestones. Stay tuned for more updates as we strive for enduring excellence in every detail of the ODOM project.