We’re excited to bring you the latest updates on ODOM’s construction progress. As part of our semi top-down method, which focuses exclusively on basement construction before moving above ground, we continue to advance deeper into the foundation of this landmark development.

Figure 1: Pre-casting preparation

At Basement Level 3, excavation is now complete, marking a key milestone in our progress. Concrete casting is well underway, with three out of the four planned blocks successfully completed. Work on this level’s fourth and final block is in progress, with formwork and rebar installation currently being carried out in preparation for the next concrete pour.

Figure 2: Rebar Installation

We are getting closer to completing the five basement levels that will serve as the strong foundation for ODOM. Our commitment to quality remains as we carefully execute each phase of construction with precision and efficiency.

Figure 3: Concrete Casting

Thank you for your continued support. Stay tuned for more updates as we advance further into this exciting stage of the project. We look forward to sharing more milestones with you soon!

10

Find Your Ideal Office Size

How many staff do you have?

Layout Type

Loading
Sample Small Offices

Sample Small Offices

Sample Medium Offices

Sample Medium Offices

Sample Large Offices

Sample Large Offices

Sample Full Floor

Sample Full Floor

We recommend a small office size of 60 to 90 sqm.

This will give you approx SQM/PAX for people in a density configuration.

We recommend a medium office size of 91 to 148 sqm.

This will give you approx SQM/PAX for people in a density configuration.

We recommend a large office size of 141 to 250 sqm.

This will give you approx SQM/PAX for people in a density configuration.

We recommend a full floor of 887 to 1,515 sqm.

This will give you approx SQM/PAX for people in a density configuration.

SCHEDULE A CONSULTATION